Team overcomes soil issues, materials delay with planning and flexibiity

the outside of a modern hotel in Alpharetta Georgia

ALPHARETTA, GA. — Soil issues, delayed materials, and COVID-19 challenged Crain Construction while teaming with Chartwell Hospitality LLC to build a new Hilton Hotel in Georgia’s Fulton County. Extreme planning and flexibility kept the project moving forward.

With some modifications, the 249-room, eight-story hotel is based on the full-service prototype Hilton Hotel the team built a couple of years ago in Franklin, Tenn. The team — Chartwell Hospitality, Rabun Architects, The W Group interior design, Crain Construction, and 50 percent of the subcontractors – was the same for both projects.

The Alpharetta hotel site was pad-ready when Crain Construction took over the project as a general contractor in May 2019. However several months into the job, work was paused to investigate and correct substandard soil causing building issues. Instead of stopping the entire project for two and a half months while the soil issue was resolved, the team tried to keep everything moving as much as possible.

“Framing, electrical, and plumbing kept marching on as we tried to mitigate the impact of stoppage on the project,” said James Williams, Crain Construction project manager.

With the investigation completed, low-mobility grouting was installed to prevent the substandard soil from further affecting the building. That allowed the construction team to proceed on the critical path of installing precast veneer.

The project hit another setback when the first COVID-19 case stopped work for 10 days. Handwashing stations were built and set up throughout the worksite and mandatory face mask use was implemented for the 150-175 workers onsite. High touchpoint areas (handrails, hoists, grabrails, equipment, portable toilets, etc.) were cleaned every night.

“We managed to keep everyone on an even keel by being ultra-transparent and communicating frequently,” said Williams. “With the fluidity of coronavirus information coming from the federal level, we met virtually with 15 subcontractor companies four or five times a week to keep everyone informed and working off the page.”

Materials were also delayed due to the coronavirus. Italian floor tile for the guest rooms and public spaces took eight months to arrive, instead of the normal six months. Furniture shipped from China was on the water for 14 weeks, instead of eight. Delays forced changes to the interior design and had the team hunting throughout the U.S. for other available materials.

“The project required extreme planning and forced us to be more flexible across the board,” said Williams. “We learned to adapt and change the way we normally do things.”

Despite the multiple challenges, Williams and his team remained client-focused and kept the project moving. The 178,000-square-foot Hilton Alpharetta opened for guests in mid-March 2021. Crain Construction’s open and ongoing communication and team dedication earned high praise from hotel leadership.

“This has been a fun project and as excited as I am to get this hotel open, I am sad to see the construction phase ending,” said Tim Zuggar, general manager of Hilton Alpharetta Atlanta– Chartwell Hospitality. “I have really enjoyed working with you and your team. You are a professional and I value the friendship we have developed.”

Related Projects

new building contructed in nashville
Breaking Down the Budget: A Developer’s Guide to Commercial Construction Costs in Nashville

Understanding the costs of construction is one of the most foundational elements of effective project planning. This is especially true in a dynamic and fast-growing city like Nashville, where property values, labor costs, and material prices have seen steady increases in recent years. Navigating these costs requires a blend of expertise, foresight, and collaboration. At...

commercial building under construction in nashville
What Developers Should Know About Building in Nashville In 2025

Nashville’s real estate market is set for an exciting year in 2025. Despite high prices and lingering challenges, the city’s commercial construction outlook remains strong. According to a recent article from The Tennessean and the 2025 U.S. Emerging Trends in Real Estate report, Nashville ranks in the top five markets to watch. The resilience of...

Double Queen (2)
Project Spotlight: Marriott Tri-Brand

As the saying goes, there’s a first time for everything. This project was not only a first for Crain Construction in our 90+ years of history but also for Nashville itself. Transforming a third-floor parking garage into 36 high-end guest suites as hotel operations continued was a groundbreaking endeavor. The final project added a new...

City Park wide angle
Innovation in Action: How Crain Construction Uses Drones for Smarter Project Management

As a 90-year-old commercial construction company, we’ve seen the importance of enhancing timeless construction principles with new tools and technology. We are intentional about always looking for ways to improve our processes and project outcomes. One recent example is the use of drones, which are transforming how we approach project management, quality assurance, and collaboration....

Community

We partner with organizations to invest, give back and make a positive impact on the communities where we live and work.

Blog

Get the latest Crain Construction Blogs and interesting insights about our projects and community endeavors here.

When you’re ready to build, we’re here for you

Reach out to start a conversation with our team.