ALPHARETTA, GA. — Soil issues, delayed materials, and COVID-19 challenged Crain Construction while teaming with Chartwell Hospitality LLC to build a new Hilton Hotel in Georgia’s Fulton County. Extreme planning and flexibility kept the project moving forward.

With some modifications, the 249-room, eight-story hotel is based on the full-service prototype Hilton Hotel the team built a couple of years ago in Franklin, Tenn. The team — Chartwell Hospitality, Rabun Architects, The W Group interior design, Crain Construction, and 50 percent of the subcontractors – was the same for both projects.

The Alpharetta hotel site was pad-ready when Crain Construction took over the project as a general contractor in May 2019. However several months into the job, work was paused to investigate and correct substandard soil causing building issues. Instead of stopping the entire project for two and a half months while the soil issue was resolved, the team tried to keep everything moving as much as possible.

“Framing, electrical, and plumbing kept marching on as we tried to mitigate the impact of stoppage on the project,” said James Williams, Crain Construction project manager.

With the investigation completed, low-mobility grouting was installed to prevent the substandard soil from further affecting the building. That allowed the construction team to proceed on the critical path of installing precast veneer.

The project hit another setback when the first COVID-19 case stopped work for 10 days. Handwashing stations were built and set up throughout the worksite and mandatory face mask use was implemented for the 150-175 workers onsite. High touchpoint areas (handrails, hoists, grabrails, equipment, portable toilets, etc.) were cleaned every night.

“We managed to keep everyone on an even keel by being ultra-transparent and communicating frequently,” said Williams. “With the fluidity of coronavirus information coming from the federal level, we met virtually with 15 subcontractor companies four or five times a week to keep everyone informed and working off the page.”

Materials were also delayed due to the coronavirus. Italian floor tile for the guest rooms and public spaces took eight months to arrive, instead of the normal six months. Furniture shipped from China was on the water for 14 weeks, instead of eight. Delays forced changes to the interior design and had the team hunting throughout the U.S. for other available materials.

“The project required extreme planning and forced us to be more flexible across the board,” said Williams. “We learned to adapt and change the way we normally do things.”

Despite the multiple challenges, Williams and his team remained client-focused and kept the project moving. The 178,000-square-foot Hilton Alpharetta opened for guests in mid-March 2021. Crain Construction’s open and ongoing communication and team dedication earned high praise from hotel leadership.

“This has been a fun project and as excited as I am to get this hotel open, I am sad to see the construction phase ending,” said Tim Zuggar, general manager of Hilton Alpharetta Atlanta– Chartwell Hospitality. “I have really enjoyed working with you and your team. You are a professional and I value the friendship we have developed.”

Related Projects

Element hotel building exterior Nashville at Dusk
Building a Better Nashville: How Crain Construction Contributes to the City's Sustainability Goals

Sustainability has become a cornerstone of modern construction, especially in urban cities like Nashville. City leaders and local residents have a shared interest in ensuring that Nashville remains a vibrant, healthy, and livable place for generations to come. This commitment is embodied in initiatives like the NashvilleNext plan, which outlines policies to guide the city’s...

Crestmoor building during construction
Crain Construction’s Top 5 Hospitality Projects

At Crain Construction, we take pride in our ability to deliver exceptional results on complex and high-profile hospitality projects. Our experience spans a variety of hotel builds, each presenting unique challenges and requiring innovative solutions. Here, we’ll walk through five of our standout hospitality projects, all of which showcase our commitment to quality, safety, and...

2 crain project engineers on construction site
Behind the Scenes: A Day in the Life of a Crain Project Engineer

At Crain Construction, we believe that every person plays a vital role in the success of our commercial construction projects. From the skilled tradespeople on-site to the project managers overseeing the big picture, it’s a team effort. But when it comes to details, technical skills, collaboration, and problem-solving, few roles are more essential than the...

Nashville Ferrari Dealership Building
Project Spotlight: Ferrari Dealership | Prancing Horse of Nashville

In the world of high-end cars, Ferrari stands as a symbol of luxury, performance, and precision. When the carmaker decided to bring their iconic brand to Nashville, they needed a facility that would reflect their high-end quality standards and brand prestige. Crain Construction’s proven expertise and commitment to quality for over 90 years made the...

Community

We partner with organizations to invest, give back and make a positive impact on the communities where we live and work.

Blog

Get the latest Crain Construction Blogs and interesting insights about our projects and community endeavors here.

When you’re ready to build, we’re here for you

Reach out to start a conversation with our team.